Austin Energy asks for $41.8 million more for two downtown projects, one of them nearly double its original price
The Brackenridge substation contract would grow to $59.9 million and the Sixth Street chilled water line to $44 million. Six more I-35 condemnations are also on the Nov. 19 agenda.
Two downtown Austin Energy construction projects need a combined $41.8 million more, according to items on the City Council's Nov. 19 agenda. The requests come days after the utility reported that it ended its budget year short of all five of its financial health targets, as we reported Wednesday.
The Brackenridge substation: $26 million more
Item 12 would add $26 million to Jingoli Power's design-build contract for the Brackenridge substation, raising it to $59.9 million. The council approved the original contract in April 2023.
The substation, downtown in ZIP code 78701, is part of what the utility calls "Repowering Downtown." The staff memo says the job replaces 1970s open-air equipment with enclosed gas-insulated switchgear to handle growing downtown demand. Crews will shut down the old substation, reroute its power, demolish it and rebuild. Deliveries may briefly affect traffic on the I-35 frontage road.
Staff wrote that "due to high costs of project equipment already purchased," more money is needed for the remaining equipment, demolition and site work. Construction is expected to start in June 2027, and the builder will price that work later. "The project team will return to council for any additional authorization needed," the memo says.
Advertisement
The Sixth Street chilled water line: nearly double
Item 13 would add $15.8 million in contingency to Primoris Energy Services' contract to extend the downtown chilled water system along Sixth Street, for a total of $44 million. The chilled water system cools downtown buildings.
The contract started at about $22.6 million in November 2024. The council added $5.6 million in December 2025, on consent. This increase brings the total to nearly twice the original.
State law limits change orders to 25% of a contract's original price. The memo says this work is exempt because it is needed to protect public health and safety and because of "unforeseen damage to public property." Crews found "tieback obstructions, existing voids, water infiltration from deteriorated infrastructure, underground structures, flooding, degraded soils, and hazardous gas," it says, and the job was hit by Winter Storm Fern, copper theft and vandalism. Tunnels are partly built and excavations are open. Completion is expected in June 2027.
Six more condemnations for I-35
Items 77 through 82 would let the city file eminent domain cases for six small electric easements, from about 520 to 1,740 square feet each, along East 38½ Street, Harmon Avenue, Cole Street, East 28th Street and Dancy Street. Austin Energy must move transmission structures on three circuits that cross I-35 for TxDOT's highway rebuild. Appraisals total about $711,000. In each case, staff say, the city and owner could not agree on a price.
Advertisement
The council approved the first three condemnations for this project on Sept. 24, 10-1. Council Member Zohaib "Zo" Qadri voted no.
What the operations report shows
Austin Energy's fourth-quarter operations report, posted for the Nov. 17 oversight committee, says:
- Carbon-free power: 64% of what the utility generated in July through September was carbon-free. As a share of customer demand, it was 56%.
- Reliability: Customers averaged 0.87 outages in the quarter, for 75.7 minutes of outage in all. The report compares that with a 2025 Texas average, from federal data, of 1.55 outages and 158.4 minutes. Major storm days are excluded.
- Home batteries: About 185 customers had Base Power batteries by October, 3.7 megawatts toward a 40-megawatt goal. The council approved that 10-year deal, about $4 million a year, 10-0 in April.
What our records add
Brackenridge was already on the list. In July, the city's budget staff told the council Austin Energy's capital spending would focus on substations at Brackenridge and McKinney Falls.
The bonds. On Nov. 5 the council approved up to $695 million in electric revenue bonds without objection.
What's next
The Electric Utility Commission was scheduled to review Items 12, 13 and 77 through 82 on Nov. 9. The oversight committee meets Nov. 17, and the council votes Nov. 19.