Austin Energy opens its home battery rewards to Tesla, Generac and Enphase owners: a $500 rebate and about $75 per kilowatt a year
The Power Partner battery pilot started in March with two brands. The utility is counting on home batteries to help reach 125 megawatts of local storage by 2035, and its separate Base Power fleet had 185 homes in October.
Austin Energy has widened its Power Partner Battery pilot, which pays home battery owners to let the utility draw on their batteries during high demand. The program started in March for SolarEdge and FranklinWH systems and now includes Tesla, Generac and Enphase batteries, the city announced Monday.
What owners get
According to the release:
- Upfront: A $500 rebate toward a home battery installed on or after Feb. 18, 2025.
- Every year: $75 per kilowatt of average output delivered during the utility's demand response events. Customers who take part in events through the year can earn more than $300 a year, the utility says.
- How it works: The batteries become part of a "virtual power plant," a network of home batteries, smart thermostats and EV chargers that the utility can call on together, as if they were one power plant.
Power Partner offers three ways for residential customers to take part, including one for electric vehicles, and the utility runs separate demand response programs such as Smart Home Rewards and Power Savers.
"Homeowner interest in battery storage has climbed dramatically in recent years," said Richard Génecé, Austin Energy's vice president of customer energy solutions.
Advertisement
What our records add
Two home battery programs. Power Partner pays customers who already own a battery. The utility's other program, a 10-year deal with Base Power approved by the council in April, puts company-owned batteries in homes: customers keep part of each battery for outages, and Austin Energy pays for and uses the rest. Slides for today's Austin Energy Utility Oversight Committee meeting counted about 185 Base Power installations totaling 3.7 megawatts as of October, out of a planned 40 megawatts. We covered those slides in our Nov. 14 preview.
The timeline. At the July 21 oversight committee, Austin Energy staff said Base Power installed its first Austin systems in late June and expected to reach the full 40 megawatts by mid to late 2027. Each new battery is added to the utility's portfolio as it's installed.
The goal. Home batteries count toward the utility's target of 125 megawatts of local storage by 2035. The council also approved a separate 200-megawatt grid-scale battery deal with Jupiter Power this year.
Why the utility wants it. Austin Energy closed its last budget year $8 million short and missed its financial health targets. Batteries that can be dispatched at peak times can reduce what the utility pays for power when prices spike on the state grid. The utility's Value of Solar credit for rooftop solar rose 27% on Oct. 1.
What's next
The oversight committee met this morning, ahead of the council's work session and election canvass; video should appear on our meetings page when the city posts it. Details on eligibility are on Austin Energy's website.