On My Block · Austin Politics

TransportationZilker

Barton Springs Road bridge: designs shown, construction pushed to 2028, and $4 million more for the designer on Dec. 3

Federal environmental review has added about two years, the city says. Two city commissions want the century-old bridge rehabilitated instead, and the District 8 member-elect leans that way too.

The city showed maps and renderings of a new Barton Springs Road bridge at an open house Monday, Nov. 16, and the design contract is headed back to the City Council for more money. The schedule has slipped since staff last briefed the council.

What residents saw

The proposed bridge has four vehicle lanes, two each way with a median, plus dedicated bike lanes and wider walkways, the Austin Chronicle reported. Below the deck along the creek, the plan widens the hike-and-bike trail, stabilizes the creek bank and makes more room for the Zilker Eagle train. Our open house preview has the council's history on the project.

The Chronicle reported that residents remain divided. Preservation Austin and the Save Our Springs Alliance argue full restoration is more viable and cost-effective, and the Environmental Commission and Historic Landmark Commission have asked the council to revisit its 2023 vote to replace the bridge. City engineers point to deterioration in the deck and columns and say rehabilitation would cost about as much as a new bridge without lasting as long.

Item 14: $4 million more for design

Item 14 on the Dec. 3 draft agenda would add $4 million to the city's design contract with URS Corporation, for a revised total of up to $15,863,005, from the transportation department's capital budget. The recommendation for action says the money covers work to finish the National Environmental Policy Act (NEPA) review, final design, bidding, award and construction-phase services.

The backup's contract history shows the contract began in 2015 at $300,000 and grew through amendments in 2017, 2021 and 2024, the last for $9 million in design services. (Its authorization table totals $15,806,005, slightly different from the $15,863,005 in the posting.)

The schedule moved

  • What staff said earlier this year: The federal review would take about a year, with staff hoping to finish at the end of 2026 and bid the project in early 2027, as our preview reported from the April Mobility Committee meeting.
  • What the Dec. 3 backup says: "The NEPA requirements have extended the anticipated project schedule by approximately two years." NEPA must be completed before the city can sign the federal Bridge Investment Program grant agreement. Remaining work includes field investigations and "coordination with state and local historic preservation authorities."
  • What the Chronicle reported: the review is expected to finish in 2028, construction could start that fall, and a public hearing is planned for 2027.

The council accepted the $32 million federal grant on April 24, 2025, 11-0, the backup says. The Chronicle reported the city also expects 2020 Mobility Bond money and that a total cost estimate has not been finalized.

The politics

The council voted in December 2023 to approve the replacement concept. By the time it acts on construction, the dais will look different:

  • District 5: Council Member Ryan Alter, in a Dec. 12 runoff, called bridge safety his top priority and said he wants to explore options within available funds, including preserving the existing structure, the Chronicle reported. His opponent, David Weinberg, supports rehabilitation.
  • District 8: Selena Xie, who takes office Jan. 6, prefers safety improvements that keep the existing bridge, the Chronicle reported, a possible shift from Council Member Paige Ellis, who voted for the replacement design in 2023.

Item 14 is on the consent agenda. Feedback on the design can go through the city's Speak Up Austin page, according to the Chronicle.