On My Block · Austin Politics

TransportationTransit

CapMetro approves up to $51.1 million to double-track the Red Line at Plaza Saltillo. The city's share pays for a trail and safer crossings on East Fifth

Construction is set to start in January and run into spring 2029, near TxDOT's I-35 work. The city's 2024 agreement with CapMetro covers up to $5 million for a shared-use path and street changes.

CapMetro's board on Monday approved up to $51.1 million to expand its Plaza Saltillo commuter rail station on East Fifth Street, CBS Austin and KVUE reported. The station now has a single track and can hold one train; the project would let up to four trains use it.

What's in the project

According to CBS Austin and KXAN's preview of the vote:

  • Contractor: Jay-Reese Contractors, recommended by staff.
  • Cost: A base construction contract of about $44.5 million plus a 15% contingency, for up to $51.1 million.
  • Track and platforms: Two 280-foot side platforms and about a mile of double track, from around Onion Street east through the "Austin Y" area toward Robert T. Martinez Jr. Street.
  • Crossings: Safety upgrades at rail crossings at Navasota, Comal, Onion, Chalmers and Robert T. Martinez streets.
  • Street and trail: A bike and pedestrian path from Chicon Street to Pedernales Street, plus reconfiguring and resurfacing East Fifth Street.
  • Schedule: Construction from January 2027 into spring 2029, with platform and track work starting in April. CapMetro says it will keep rail service to downtown during construction and start community outreach before the end of this year.

The money comes from CapMetro's capital budget, an $18 million federal grant and up to $5 million from the City of Austin for the path and crossing work, CBS Austin reported. CapMetro said it coordinated with TxDOT so TxDOT can build its Fourth Street rail overpass for I-35 at the same time.

"We were no longer able to comfortably accommodate all of the passengers who want to use commuter rail in this area," said Ken Cartwright, CapMetro's vice president of construction and facilities.

What our records add

The city's piece. The city's share traces to an interlocal agreement with CapMetro that was on the council's Nov. 21, 2024 agenda as item 69. The staff backup says:

  • The city and CapMetro applied together for the federal grant, which was awarded for up to $18 million.
  • The city's up to $5 million pays for a shared-use path and striping on East Fifth Street from Chicon Street to Robert T. Martinez Jr. Street. The city planned to build the segment from Robert T. Martinez to Pedernales separately.
  • CapMetro builds the city's pieces as part of its rail work, so the street isn't torn up twice. The agreement listed up to $30.2 million in CapMetro improvements at the time.
  • The path extends the Red Line Trail, a top-tier trail in the council's Urban Trails Plan.
  • The agreement's first term runs through September 2028. With construction now scheduled into spring 2029, it may need an extension.

Station-area planning. At the Oct. 1 Mobility Committee, city planning staff said the council has directed them to update the three existing transit-oriented development plans along the Red Line. Plaza Saltillo has had its own station area plan since 2008; the council has amended it several times for nearby rezonings.

What's next

CapMetro says outreach starts before January. Any extension of the city's agreement or added city money would come back to the council.