At a 42-minute meeting Thursday, staff updated the committee on the downtown street plan adopted in March. Committee members asked about public input, the Third Street bikeway and speeds on the rebuilt I-35 frontage roads.
The City Council's Mobility Committee met for 42 minutes Thursday afternoon, Nov. 12, and heard an update on the downtown street plan the council adopted in March. City staff said rebuilding Sixth Street between Congress Avenue and I-35 would cost more than $60 million, that Seventh Street will carry traffic both ways, and that Eighth Street will flip direction before TxDOT finishes rebuilding I-35.
Chair Paige Ellis, Vice Chair Zohaib "Zo" Qadri and Council Member Krista Laine attended. Mayor Pro Tem José "Chito" Vela, the committee's fourth member, was not there. Our preview covered the agenda.
The downtown plan, six months in
The Austin Core Transportation (ACT) Plan is the downtown piece of the city's long-range mobility plan. Assistant Director Anna Martin of Transportation and Public Works said it carries more than $1 billion in needed capital spending over 20 years. Her presentation lists four priority streets:
- Fifth and Sixth, Lamar to Congress. Conceptual design is underway, with public engagement in 2027. "There's no capital funding currently identified for this work," Martin said.
- Sixth, Congress to I-35. Engineers have picked a preferred design for the nine blocks of the entertainment district, with more room for people walking and loading space for businesses. Martin put the cost at over $60 million. The city is looking at building it in phases, with grants or private developers paying for some blocks.
- Seventh. Its four eastbound lanes carry heavy afternoon traffic to I-35. Once ramps change, that traffic is expected to shift to Eighth, and Seventh will serve both directions. A preliminary engineering recommendation is due in early 2027.
- Eighth. It becomes the main route to northbound I-35 and must be converted from one-way westbound to one-way eastbound. TxDOT will pay for interim work on both streets, which must be in place by 2033.
Martin also said the first phase of the Congress Avenue project, with wider sidewalks and protected bike lanes from Cesar Chavez to Seventh, is being built block by block and should be done in late 2027.
Advertisement
What members asked
Public input. Qadri, whose district covers much of downtown, asked what engagement on Fifth and Sixth would look like. Martin said staff would work block by block with businesses. Qadri, just off the campaign trail, said he often hears that people don't feel part of the process.
One-way or two-way. Qadri noted every street drawing was one-way. Martin said short-term concepts keep Fifth and Sixth one-way, but the plan commits to evaluating two-way conversions when a whole corridor is redesigned. Asked for a rough timeline on East Sixth, she said, "I don't right now."
The Third Street bikeway. Light rail will take Third Street, so the Lance Armstrong Bikeway is moving to Fourth. Ellis asked when. Martin said ATP has the city's schematic, but she did not have a firm commitment that Fourth would be finished before work starts on Third, only a commitment that people can keep riding safely through downtown.
Frontage road speeds. Ellis asked about speed limits on the rebuilt I-35 frontage roads. Martin said TxDOT has been open to slower designs and the city controls signal timing, but there is no firm commitment on a posted speed.
Advertisement
The rest of the meeting
- Minutes. The committee approved the Oct. 1 minutes and the corrected 2025 and February minutes without discussion. Our preview found a second list of future items in the Oct. 1 draft that our transcript of that meeting does not show. Nothing said Thursday indicated whether the approved version was changed.
- 2027 calendar. Members approved seven meetings for next year, starting Feb. 18.
- Director's report. Ellis highlighted a 39% drop in deadly and serious crashes on residential streets after the 25 mph default limit. The monthly report also says a 60% draft of the citywide lighting plan is due in December.
- What's coming. Ellis said a CapMetro bike share update and a briefing on possible FAA flight path changes were postponed. Laine asked for a transportation briefing from the city's government relations team, given "how much the political landscape has changed."
The meeting began with four public speakers about JD's Supermarket and light rail; our separate story covers that. The Urban Transportation Commission's Parmer Lane recommendation is here. Ellis adjourned at 1:45 p.m.
Ellis's term ends in January. The committee's next scheduled meeting is Feb. 18, after the new council is seated.
Times in links are from the city's video; our meeting page adds the full transcript once it is posted.