South Lamar's 2016 bond rebuild from U.S. 290 to Montclaire Street goes to the council: $27.5 million, nearly three years of work
The low bidder of five, Joe Bland Construction, would build shared-use paths, new bus stops, signals and drainage on a mile and a half of South Lamar. One lane each way stays open.
Another stretch of South Lamar Boulevard from the 2016 bond program is ready for a construction contract. Item 17 on the council's Dec. 3 consent agenda would hire Joe Bland Construction to rebuild about 1.5 miles of South Lamar from U.S. 290 to Montclaire Street for $24,996,956, plus a 10% contingency of $2,499,696, for a total of up to $27,496,652.
The project is part of the 2016 Mobility Bond Corridor Program, according to the recommendation for action.
What would be built
The backup lists:
- New curbs and gutters, and sidewalks, ramps and shared-use paths that meet the Americans with Disabilities Act.
- Repaving parts of the road, new traffic signal equipment, and relocated and new bus stops.
- Storm drains: about 2,900 feet of round pipe and 1,700 feet of box pipe.
- About 1,270 feet of new water mains and 2,500 feet of wastewater mains.
- Street trees, landscaping, rain gardens, signs, striping and some new medians.
The contract includes $40,000 for handling contaminated soil and groundwater and $46,500 for moving private service lines.
Advertisement
Who pays
- Austin Transportation and Public Works: $21,047,718
- Watershed Protection: $5,359,607
- Austin Water: $1,089,327
What it means for drivers and businesses
Expect lane closures, detours and temporary pavement. Staff say "a minimum of one lane of traffic in each direction will be maintained at all times," driveways will stay open, and property owners will get at least 48 hours' notice of planned water or other service interruptions. The contract allows 1,044 calendar days, nearly three years, to finish. The city says it will send mailings and use social media to tell neighbors what's coming.
"A delay in issuing this contract will affect the delivery of mobility improvements for South Lamar Blvd.," the backup says.
How the bid went
The city advertised the job July 6 and opened bids Sept. 24. Joe Bland's was the lowest responsive bid of five. The contract meets the city's minority- and women-owned business goals with 8.85% and 3.74% participation, according to the MBE/WBE summary. The Water and Wastewater Commission recommended it 6-0 on Nov. 10, with one member off the dais, three absent and one seat vacant.
The neighborhood around it
The segment runs through ZIP code 78704 in District 5, whose council seat is in the Dec. 12 runoff. The same Dec. 3 agenda includes a nearby rezoning at 3415 Menchaca Road, where an owner wants to replace 16 apartments with up to 60 under the city's density bonus program; our zoning roundup has details. The city's planning staff describe that site as about an eighth of a mile from the MetroRapid line on South Lamar.
The full agenda is in our Dec. 3 guide, and the final agenda changes are here.