Walnut Creek on Dec. 3: $9.6 million for 3.8 miles of trail in Northeast Austin and a TxDOT deal for a bike bridge on North Lamar
The Northern Springdale segment of the Northern Walnut Creek Trail drew 12 bids. Separately, a walking and biking bridge over the creek on North Lamar needs a maintenance agreement with the state.
Two items on the council's Dec. 3 consent agenda would move walking and biking routes along Walnut Creek forward, one in District 1 and one in District 7.
The Springdale trail segment (Item 16)
The city would hire M.A. Smith Contracting to build the Northern Walnut Creek Trail's Northern Springdale Corridor section for $8,699,656, plus a contingency of $869,966, for up to $9,569,621, according to the recommendation for action.
What the backup says about it:
- 3.78 miles of 12-foot-wide paved path for walking and biking, built to the city's "All Ages and Abilities" standard, plus a bridge over Walnut Creek.
- It would connect the Southern Walnut Creek Trail to Braker Lane and nearby on-street bike routes, a "critical remaining connection" in a planned 20-mile trail network linking North and Southeast Austin.
- It is paid for by the 2020 Mobility Bond and a $5 million federal grant that the backup credits to U.S. Rep. Lloyd Doggett. Staff warn that a delay "could impact the project's grant funding."
- Work would be on undeveloped land and the abandoned MoKan rail corridor, in ZIP codes 78754 and 78724, with some segments outside the city limits. Traffic effects should be limited to construction vehicles.
- The contract includes $598,500 to test for and treat sulfate in soils, if found, and allows 655 days for completion.
The city received 12 bids; M.A. Smith's was the lowest responsive one. No minority- or women-owned business goals were set for this job.
Advertisement
What our records show. In October 2025, the council voted 10-0, with one member absent, to file eminent domain for trail easements on about 1.2 acres at 9345 E. U.S. 290 for what that item called the Northern Walnut Creek Trail Phase Three, connecting the northern and southern trails "under East United States Highway 290, between Springdale Road and Johnny Morris Road." The easements were appraised at $217,855. The Dec. 3 backup does not say whether that phase and this contract cover the same stretch.
A bridge on North Lamar (Item 41)
The city is rebuilding the North Lamar corridor and wants to add a pedestrian and bicycle bridge over Walnut Creek, running alongside North Lamar on the east side of the road. Part of it would sit in Texas Department of Transportation right of way, so the city needs a "multiple use agreement" with TxDOT that sets out who maintains what, according to the recommendation. The project would also extend TxDOT's standard pedestrian rail and metal guard fence on the southwest side.
The agreement itself costs nothing, staff say. Construction is scheduled from Sept. 15, 2027, to Aug. 15, 2028, in District 7.
What our records show. In April the council voted 10-0, with one member absent, to file eminent domain for a sidewalk and trail easement at 12101 N. Lamar Blvd. for the same corridor project, on a route "crossing over Walnut Creek between Walnut Park Crossing and Oakbrook Drive." That easement was appraised at $8,984. The owner listed is Pleasanton Housing Finance Corporation.
Item 41 has its own page, and both items are listed in our Dec. 3 agenda guide.