On My Block · Austin Politics

ParksCity Hall

Austin would pay $1.6 million for three Brentwood lots to make a park, and lend part of Hancock Golf Course to I-35 water line work for 18 months

Both parkland items are on Thursday's agenda. The Brentwood purchase uses parkland dedication fees; the Hancock plan closes the seventh tee area until late 2028 and pays Parks $188,215.

Two parkland items on the City Council's Nov. 19 agenda pull in opposite directions: one adds a small park in Brentwood, the other lends part of Hancock Golf Course to the I-35 rebuild.

A new park on Ullrich Avenue

Item 45 would let the city buy about 0.68 acres at 1902, 1904 and 1906 Ullrich Avenue, at the rounded corner of Ullrich Avenue and Laird Drive, just off West Koenig Lane and Burnet Road. The staff backup says:

  • Price: An independent appraisal supports $1,608,750. With closing costs the total is capped at $1,634,550.
  • Seller: GDC-NRG Koenig LLC.
  • What's there: Three single-family homes, which would be torn down, and shade trees, including two heritage trees along Ullrich. None of the land is in a flood hazard area.
  • Who it serves: 661 Brentwood residents who don't have a park within reach now, according to staff.
  • Money: Parkland dedication fees, the charges developers pay in place of providing parkland. No general fund money.

The site is in District 7.

Hancock Golf Course and I-35

Item 86 is a public hearing required by state law before the city can use dedicated parkland for something other than a park. Austin Water would use about 9,482 square feet of District 9's Hancock Golf Course as a staging area for moving water and wastewater lines out of TxDOT's path between Martin Luther King Jr. Boulevard and Holly Street.

The memorandum between Austin Water and Parks lays out the terms:

  • Start: About May 1, 2027, for 549 days.
  • Reopening: Estimated Oct. 31, 2028, after restoration and inspection.
  • The course: Parks will restore the area, including re-establishing the seventh tee.
  • The trail: A temporary 8-foot pedestrian path and detour signs, with signs posted seven days before the detour starts.
  • Payment to Parks: $188,215, made up of:

- $124,546 for temporary use, at a daily rate of $227 based on nearby land values - $29,097 for site preparation and restoration - $14,947 to replant trees after the project - $10,402 to transplant existing trees - $9,223 for the "sunken cost" of existing trees

If the work runs long, Austin Water pays more at the daily rate. TxDOT's contractors would do the construction. The Parks and Recreation Board recommended the plan 9-1 on Sept. 28. Under Chapter 26 of the Parks and Wildlife Code, the council must find there is "no feasible and prudent alternative" and that harm to the park has been minimized.

What our records add

Less money for land. At the July 20 Audit and Finance Committee, Mayor Pro Tem José "Chito" Vela said the city has "lost sources of revenue for capital projects in parks" because of limits the Legislature put on parkland dedication fees. Voters approved new parks and library bonds on Nov. 3.

More I-35 parkland deals. The same Nov. 19 agenda has a $25 million TxDOT-funded Lady Bird Lake boardwalk and four agreements to move water lines for the highway. The council is also set to vote Dec. 3 on East Avenue Trail landscaping.

What's next

Both items are scheduled for Thursday, Nov. 19. Item 86 has a public hearing; speakers can sign up on the city's council meeting page.