On My Block · Austin Politics

ParksI-35

TxDOT would pay $25 million for a Lady Bird Lake boardwalk behind the Hyatt, as part of what it owes for I-35

The boardwalk would fix a narrow, eroding stretch of the Butler Trail. The city would pay any overruns. A separate hearing lets Austin Water use part of Hancock Golf Course for I-35 line work.

The state would pay $25 million for a new boardwalk over Lady Bird Lake behind the Hyatt Regency, fixing one of the tightest spots on the Butler Hike-and-Bike Trail, under an agreement the City Council takes up Nov. 19. The money is part of what TxDOT owes the city for the I-35 rebuild.

Item 52 would approve an advance funding agreement with TxDOT, accept the $25 million and put it in the parks capital budget. Item 11 would hand the design and construction to the Austin Public Facilities Corporation, a corporation the city created to finance and build public facilities.

The pinch point

According to the staff memo, the "Riverside Shores Boardwalk" would run along the south shore between South First Street and South Congress Avenue, north of the Hyatt. Staff describe the trail there as narrow, with a sharp turn and a steep grade. It conflicts with boat dock operations and suffers from standing water and cliff erosion.

The project calls for:

  • a 14-foot trail with 2-foot shoulders, with options for a double trail or slow zone;
  • a boardwalk over the water;
  • stabilizing the eroding cliffs and banks.

Staff say the trail gets about 5 million visits a year, the most of any in Austin. The project was identified in the 2021 Butler trail safety and mobility study done with The Trail Conservancy.

Who pays and who runs it

  • TxDOT pays a fixed $25 million from the Texas Mobility Fund. It reviews the design, procurement and construction award, and it can audit.
  • The city pays nothing up front, staff say, as long as there are no utility relocations or land costs and the project stays within $25 million. The city is responsible for 100% of any overruns. Any savings go back to TxDOT. Staff say the boardwalk "will be designed to the available budget."
  • Transportation and Public Works maintains the structure. The Trail Conservancy handles operations, general upkeep and programming.

If the city does not sign, staff wrote, the boardwalk "will be removed" from TxDOT's final environmental decision for the highway through a reevaluation.

A golf course for water lines

The same agenda has another I-35 item on parkland. Item 86 is a state-required public hearing to let Austin Water use about 9,482 square feet of Hancock Golf Course to build infrastructure for moving water and wastewater lines out of the highway's path.

Austin Water would pay the parks department $188,215 for the temporary and permanent use, according to the memo. State law requires the council to find "no feasible and prudent alternative" to using the parkland. The Parks and Recreation Board recommended it 9-1 on Sept. 28.

What our records add

The highway's other bills. The same agenda has four advance funding agreements for moving water and wastewater lines out of TxDOT's way, and six condemnations for Austin Energy's I-35 line work.

Earlier mitigation. Austin Water's I-35 work has used parkland before; our Waller Beach story explains.

The public facilities corporation. The council created it in March 2023. On Nov. 19 the same item also gives it $11.4 million for Austin Water's Tracor Lane campus.

What's next

The council votes Nov. 19. Under the agreement, TxDOT releases engineering money when the agreement is signed and the construction money when the design reaches 90%. The memo gives no construction date.

The boardwalk is in District 9, represented by Council Member Zohaib "Zo" Qadri.