On My Block · Austin Politics

City HallData centers

The data center ordinance is posted: a council-approved license for big server halls, night noise limits, no applications until June

The draft for Dec. 3 covers data centers with 100,000 square feet or more of server space, requires a public hearing before any license, limits generator testing to weekday daytime and makes violations a Class C misdemeanor.

Austin's first data center rules are now in writing. The city posted the draft ordinance Friday as Item 32 on the Dec. 3 draft agenda. It would add a new article to City Code Chapter 4-16, the business rules for commercial facilities, requiring a city license to operate a large data center.

In October we covered the staff memo promising this step. Council Member Mike Siegel told KXAN then that he expected a ban on large data centers in December. The posted draft does not ban them. It sets a licensing process with operating standards, and leaves zoning, meaning where data centers could go, to a second round of rules in spring 2027.

Who it covers

The draft ordinance applies to a data center "with one or more data halls that total 100,000 or more square feet" and that is the subject of a development application submitted on or after Dec. 3, 2026. A data hall is "the portion of the facility where servers are housed." As written, a data center whose development application came in before that date falls outside the new article.

A data center is defined by an industry code for computing infrastructure, data processing and web hosting. It excludes software publishing and streaming.

How a license would work

  • An operator applies on a city form and pays a fee set by a separate ordinance.
  • The council holds a public hearing and decides whether the data center "can be operated to achieve the standards."
  • Notice goes out by newspaper and by mail at least 15 days ahead to the applicant, owners within 500 feet and the city's community registry. The applicant must post a sign at least 10 days before.
  • The city may not accept any application until June 1, 2027.

The operating standards

A licensed data center would have to:

  • keep exterior lights fully shielded and pointed down;
  • use equipment that "reduces heat impacts on adjacent sensitive uses";
  • use the "best available technology for water efficient cooling" and reclaimed or reused water for non-drinking needs;
  • make "commercially reasonable efforts" to install on-site carbon-free generation "if technically feasible."

Noise and generators

  • At the data center's property line: no more than 55 dBA from 7 a.m. to 10 p.m. and 45 dBA from 10 p.m. to 7 a.m.
  • Low-frequency hum, measured at the neighbor's property line: 73 dBC by day and 68 dBC at night, plus a 55 dB cap in the 16, 31.5 and 63 Hz bands.
  • Generator testing: not on weekends, and on weekdays only from 7 a.m. to 7 p.m.

A violation would be a Class C misdemeanor.

What it doesn't do

  • Zoning. The recommendation for action says land use rules are expected in 2027. The October memo set a timeline of a public draft in February or March, a joint Planning Commission and council meeting in March, and council action in April or May.
  • Power and water hookups. The memo says state law requires Austin Energy and Austin Water to serve customers in their service areas. As of Sept. 30, Austin Energy had 13 inquiries of 20 megawatts or more, none above 75. Until the rules are in place, the utilities are to keep giving the council monthly notice of requests above 20 megawatts of power or 85 million gallons of water a year.
  • Large water users generally. Austin Water plans to bring a separate high-impact water user framework to the council's Climate, Water, Environment, and Parks Committee on Dec. 9, the memo says.

The data center already in view

The memo names the "Project Cosmos/Highpoint 2222 campus" at the former 3M site as one of three medium-size projects already in Austin Energy's construction process. The Environmental Commission took up 17 proposed conditions for it on Nov. 18. The draft ordinance does not name any project.

The effective date is left blank in the draft. The ordinance is listed under Austin Planning; the lead contact is Assistant City Manager Eric A. Johnson.