Council accepts $25 million from TxDOT for the Lady Bird Lake boardwalk on consent, after speakers asked for a separate vote

Velásquez voted no and Duchen abstained. The city takes on any cost overruns and long-term maintenance. Mayor Pro Tem Vela asked staff to find the lake's tour boats another launch.

The City Council on Thursday, Nov. 19, accepted $25 million from TxDOT to build a boardwalk over Lady Bird Lake behind the Hyatt Regency, part of the state's mitigation for the I-35 rebuild. Both pieces passed on the consent agenda, without a separate vote, after seven people spoke with concerns, several of them asking the council to pull the items or delay them.

  • Item 52 approves the advance funding agreement with TxDOT, accepts the money and adds it to the parks capital budget.
  • Item 11 hands design and construction to the Austin Public Facilities Corporation, for up to $25 million. The same item gives the corporation up to $11.4 million to prepare 6500 Tracor Lane for Austin Water.

Council Member José Velásquez voted no on both. Council Member Marc Duchen abstained on both, according to the mayor's announcement in the transcript. Neither explained his vote from the dais.

Our preview covers the project itself: a 14-foot trail with 2-foot shoulders between South First Street and South Congress Avenue, where staff say the trail is narrow, steep and eroding.

What the city signed up for

The staff backup spells out the split:

  • TxDOT pays a fixed $25 million from the Texas Mobility Fund. Any money left over goes back to the state.
  • The city is responsible for "100 percent of any cost overruns exceeding the $25 million state limit," plus any utility, right-of-way or easement costs. Staff wrote that the project "will be designed to the available budget, and no additional funds will be needed."
  • Transportation and Public Works maintains the structure long-term. The Trail Conservancy handles operations, general upkeep and programming.

The money arrives in two steps: TxDOT releases the engineering budget when the agreement is signed and the construction money at 90% design. If the city had declined, staff wrote, the boardwalk would have been taken out of the highway's final environmental decision.

What speakers asked

Speakers raised four main points, according to the transcript. We are not naming them.

  • Process. Several said the idea came from the private developer next door and The Trail Conservancy, not the parks department, and asked how it reached TxDOT. One read from 2023 emails she said showed the conservancy forwarding the developer's boardwalk design to TxDOT. The staff backup says the project was identified in a 2021 trail safety study done by the city and the conservancy.
  • East Austin parks. Several argued that I-35 mitigation money should go to parks east of the highway, which they said have long-unfunded master plans.
  • Who benefits. Several said the boardwalk would mainly serve the condo tower being built next to the hotel.
  • The boats. The owner of a tour boat business on the lake said she had not been able to learn how the boardwalk would affect her dock. She asked the council to direct staff to keep longtime lake businesses in the plans "both during construction and in the final design."

Vela on the boat launch

Mayor Pro Tem José "Chito" Vela was the only council member to speak on the boardwalk. "I do think it's extremely important as part of this process that we find another place where the boats can launch," he said, calling the boat rides "an almost iconic part" of Austin. He asked staff to make sure people "continue to have the opportunity... to get out on the water."

No council member asked staff questions about the project in public. The backup does not say where the boats would go.

What's next

The public facilities corporation will hire designers, subject to TxDOT review and approval of procurement and plans. Staff have not given a construction date.